锦屏二级水电站发电机主保护设计  被引量:6

Main Protection Design of Hydraulic Generators in Jinping Ⅱ Hydropower Station

在线阅读下载全文

作  者:刘正国[1] 黄锐[2] 桂林[3] 

机构地区:[1]二滩水电开发有限责任公司,四川省成都市610051 [2]华东勘测设计研究院,浙江省杭州市310014 [3]电力系统国家重点实验室清华大学电机系,北京市100084

出  处:《水电自动化与大坝监测》2011年第3期48-51,共4页HYDROPOWER AUTOMATION AND DAM MONITORING

摘  要:结合锦屏二级水电站水轮发电机的特性,通过对水轮发电机全面的内部短路分析计算、定量化的设计过程,完成了主保护配置方案的设计,保护方案性能优异。实现了水轮发电机保护无动作死区,而且对所有实际可能发生的内部故障有2种及以上不同原理的主保护灵敏动作,为大型水电站水轮发电机的安全运行提供了可靠保证。Based on the characteristic of JinPing Ⅱ Hydropower Station hydraulic generators,the design of main protection configuration scheme for hydraulic generators of JinPing Ⅱ Hydropower Station is completed through overall internal short-circuit calculation and quantitative design process.The protection performance is excellent.It implements not only no dead zone for protection act,but also more than two kinds of main protection acting for any internal fault.So it is helpful to provide reliable assurance for safe operation of large generators.

关 键 词:水电站 大型水轮发电机 内部短路计算 主保护配置方案 定量化设计 

分 类 号:TV74[水利工程—水利水电工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象