基于Shapley值的多交叉事件延误索赔责任研究  被引量:4

Research on delayed claim responsibility of multi-event intersected interference based on Shapley value

在线阅读下载全文

作  者:崔东红[1] 姚莉[1] 杨榕[1] 

机构地区:[1]沈阳工业大学管理学院,沈阳110870

出  处:《沈阳工业大学学报(社会科学版)》2011年第3期234-237,共4页Journal of Shenyang University of Technology(Social Sciences)

基  金:沈阳市政府软科学基金项目(1091199-5-00)

摘  要:索赔是承包商和业主之间承担风险比例的合理再分配,多交叉事件干扰引起的索赔是工期索赔中的难点问题,共同责任分摊成为双方争论的焦点。针对多主体、多事件交叉干扰下的工期索赔责任归属难以判断和责任比例难以预测的问题,运用多人合作博弈的思想,基于Shapley值的工期延误分析法,首先通过Shapley值将延期责任分摊到各个活动,然后根据干扰事件的起因将延期责任在业主和承包商之间进行分摊,最后通过修正系数对延期责任进行再分摊。Claim is a reasonable re-distribution of the risk ratio between the contractor and the owner.For the difficulty of claim caused by multi-event intersected interference during project delayed claim,the allotment of common responsibility becomes the focus of dispute.Considering the difficulty of estimating responsibility ascription and assessing responsibility proportion of project delayed claim in multi-subject and multi-event intersected interference,the thoughts of collaborative game is applied,and the analytical method of project delay based on Shapley value is utilized.The project delayed responsibility is allotted to each single activity by Shapley value firstly,and is allotted between the owner and the contractor according to the origin of interference event secondly,and is re-allotted through correction factors at last.

关 键 词:工期索赔 索赔分摊 延期责任 责任分摊 责任比例 多交叉事件 SHAPLEY值 合作博弈 

分 类 号:C931[经济管理—管理学]

 