江坪河面板堆石坝垫层区采用翻模固坡技术数值模拟  

Numerical simulation of application of turned-over formwork slope-fixing technology in faced rockfill dam cushion zone of Jiangpinghe hydropower project

在线阅读下载全文

作  者:张岩 

机构地区:[1]国电大渡河流域水电开发有限公司,成都610041

出  处:《西北水电》2011年第4期88-91,共4页Northwest Hydropower

摘  要:由于工期紧、施工质量要求高,江坪河水电站面板堆石坝垫层区拟采用翻模固坡技术。在正式施工之前,对面板堆石坝进行数值模拟计算,预测堆石坝体在不同分期条件下的变形和应力,从而预留出合理的变形值,能够减少面板的开裂、脱空。Due to tight construction time and requirement of high construction quality,it is proposed to use turned-over formwork slope-fixing technology in the faced rockfill dam cushion zone of Jiangpinghe hydropower project.Before formal construction,numerical simulation calculation of faced rockfill dam is carried out so as to predict dam body deformation and stress under different staged conditions,and provide rational deformation values,which can reduce face cracks and voids.

关 键 词:江坪河水电站 面板堆石坝 翻模固坡 数值模拟 

分 类 号:TV52[水利工程—水利水电工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象