炼钢厂转炉除尘系统存在的问题及其整改方案  

Existing Problems and Rectifying Plan of Converter Dedusting System of Steel-making Plant

在线阅读下载全文

作  者:陈学文[1] 

机构地区:[1]天津钢铁集团有限公司炼钢厂,天津300301

出  处:《天津冶金》2011年第4期34-37,69,共4页Tianjin Metallurgy

摘  要:转炉除尘设备冷却水及净化水为浊环水,原设计压力为0.5MPa。转炉循环水泵站按照T字形垂直合并到一趟管道并网供水,使给水压力达不到设计要求,仅为0.29MPa,除尘效果差。通过计算管道沿程阻力损失,校核泵的扬程和选配电机功率等,并对除尘系统管路进行综合优化,使系统压力提高,满足转炉出点环保要求。The cooling water and purified water for converter dedusting equipment was turbid circulating water with 0.5 MPa designed pressure.Converter circulating water pump station had its pipeline running in 'T',which merged into one line to supply water.Consequently,water supply pressure,which was only 0.29 MPa,could not meet design requirement and resulted in bad dedusting effect.The pump lift was calibrated and motor frequency chosen according to the calculation of pipeline resistance and loss.The pipeline of dedusting system was optimized to raise system pressure.Thus the converter discharge met environmental protection requirement.

关 键 词:转炉 除尘 系统 管路 循环水 损失 校核 

分 类 号:TF341.1[冶金工程—冶金机械及自动化]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象