锦屏一级水电站坝基无盖重固结灌浆施工工艺探讨  被引量:11

Discussion on Construction Technology of Consolidation Grouting without Concrete Covering for Dam Foundation in Jinping 1 Hydropower Station

在线阅读下载全文

作  者:杨世伟[1] 李德勇[1] 

机构地区:[1]四川准达岩土工程有限责任公司,四川成都610072

出  处:《探矿工程(岩土钻掘工程)》2011年第8期56-58,63,共4页Exploration Engineering:Rock & Soil Drilling and Tunneling

摘  要:锦屏一级水电站大坝由于基础层混凝土仓面面积大,温控要求严格、间歇期短,固结灌浆施工与坝体混凝土温控存在较大矛盾,主要采取无盖重固结灌浆加有盖重补强固结灌浆及引管的方式进行。主要就无盖重固结灌浆主要存在问题进行了分析和探讨。In Jinping 1 hydropower station,because of large concrete surface of dam foundation,strict temperature control,short construction interval and the contradiction between consolidation grouting and concrete temperature control,both consolidation grouting without concrete covering and reinforced consolidation grouting with concrete covering were adopted.The paper analyzed and discussed the main problems of consolidation grouting without concrete covering.

关 键 词:水电站坝基 无盖重固结灌浆 锦屏一级水电站 

分 类 号:TV543[水利工程—水利水电工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象