特高压多分裂导线同步展放双滑车悬挂新方法  

New Method for Synchronized Exhibition and Double Pulley Hanging of Ultra-high Voltage and Multiple Fission Wire

在线阅读下载全文

作  者:景国明[1] 陶春蓉 

机构地区:[1]河南送变电建设公司,郑州市450051 [2]河南电力博大工程设计有限公司,郑州市450051

出  处:《电力建设》2011年第10期97-100,共4页Electric Power Construction

基  金:国家电网公司科技项目(特高压线路无人直升机巡线装备及技术方案研究)

摘  要:±800kV云广特高压直流线路工程采用6分裂大截面导线,采用"一牵4+一牵2"同步展放方式经济合理,但每相须挂2个导线放线滑车。介绍了利用导线六联板作滑车挂点的双滑车悬挂新方法。The wires with large cross section and 6 fissions are applied in ±800 kV Yunnan-Guangdong ultra-high voltage DC transmission line project. It is shown that the synchronized exhibition of one-pulling-four combined with one-pulling-two is economic and reasonable. However, each phase must hang two pulleys for exhibiting the wires. Therefore, a new method for double pulley hanging wires is proposed where the six joint board of the wire is used as the pulley hanging point.

关 键 词:特高压线路 同步展放 双滑车 悬挂方法 

分 类 号:TM752[电气工程—电力系统及自动化]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象