渡吊技术在积石峡水电站水轮机座环吊装中的应用  被引量:1

Application of Crossing-hanging-lifting Technology in the Installation of Stay Ring for Jishixia Hydropower Station

在线阅读下载全文

作  者:李永强 张春海[2] 王英 

机构地区:[1]中国水利水电第十工程局机电安装分局,青海循化811100 [2]黄河上游水电开发有限责任公司工程建设分公司,青海西宁810000 [3]中国水利水电第四工程局机电安装分局,青海循化811100

出  处:《水力发电》2011年第11期81-82,86,共3页Water Power

摘  要:在大、中型水电站建设前期,往往遇到厂房桥机尚不具备或现场起吊设备不能满足吊装水轮机座环的难题。积石峡水电站曾面临同样的难题,在施工单位经过科学精密的计算和精心组织,采用了人字桅杆渡吊的方法将3台机组座环安全、顺利地吊装就位,确保了电站3台机座环安装及发电节点工期的圆满完成。In the early construction period of large and medium-sized hydropowcr stations, the installation of stay ring of turbine is a problem because there is no bridge crane or the lifting equipments in situ which can meet the requirements. This problem is also faced in the installation of stay rings in Jishixia Hydropowcr Station. After scientific calculation and careful organization, the crossing-hanging-lifting lechnology with a herringbone bridging is used to install the stay rings of three units. The installations arc successful and guarantee the installation duration.

关 键 词:水轮机 座环 渡吊技术 积石峡水电站 

分 类 号:TK730.313[交通运输工程—轮机工程] TK730.6[动力工程及工程热物理—流体机械及工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象