机构地区:[1]中铁二十五局集团第五工程公司,山东青岛266000
出 处:《铁道标准设计》2011年第B12期129-132,共4页Railway Standard Design
摘 要:黄土隧道下穿高速公路是本项目最大的风险源,介绍超短台阶法在下穿高速公路施工中的成功案例。通过施工总原则、主要工序施工控制、量测监控等多方面手段,达到有效控制该段隧道沉降值、在保证施工质量与安全基础上快速通过的目的。该隧道下穿高速公路共64.1 m,54 d下穿通过,施工结果表明,地表最大沉降值为17.1mm,实现了下沉控制在20 mm内的设计沉降目标,顺利完成重点工程安全质量进度目标。Construction of a loess tunnel under-passing an expressway constituted the biggest risk source of the project.This paper introduces the successful application of ultra-short bench method in tunnel construction under-passing an expressway.By means of following general construction principles,controlling main construction procedures and settlement monitoring,effective control of tunnel settlements and fast under-passing 64.1m expressway were achieved within 54 days with good quality and safety.Construction results showed that the maximum surface settlement of the under-passing section was 17.1mm which was less than the designed settlement of 20mm,thus the general goal of safety,quality as well as advance rate for the key project was achieved.
分 类 号:U455.4[建筑科学—桥梁与隧道工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.15