机构地区:[1]阳西海滨电力发展有限公司,广东阳江529800 [2]西安热工研究院有限公司,陕西西安710032
出 处:《热力发电》2012年第1期77-79,共3页Thermal Power Generation
摘 要:针对阳西电厂超临界600MW机组一次调频控制功能存在的发电机出口频率与电网辅助系统考核频率的差异、频率变送器精度偏差、机组负荷小幅波动时一次调频动作准确率低等问题进行了减小一次调频的动作死区等优化,优化后一次调频动作正确率达到99.92%以上,合格率考核电量为0。Directing against the problems existing in control function of first frequency modulation (FFM) for supereritical 600 MW unit in Yangxi Power Plant,such as the difference between exit fre- quency of the generator and the checked frequency in auxiliary systems of the power gird, the deviation of frequency transmitter's precision,and the low accuracy in actuation of FFM during the time of unit's load small fluctuation,etc.. Optimization of control function has been carried out to reduce the dead- band area in FFM. After optimization,the correct rate of actuation in FFM reaches about 99. 920/oo ,the qualified rate of checked electricity amount being zero.
关 键 词:超临界 600 MW机组 一次调频 频率控制 动作死区
分 类 号:TK323[动力工程及工程热物理—热能工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.40