“十二五”期间云南向南方电网送电曲线研究  被引量:8

On the Electric Power Transmission Curve from Yunnan to China Southern Power Grid During the "12th Five-Year" Period

在线阅读下载全文

作  者:陈谦 刘世宇[2] 曹发文 章超[4] 

机构地区:[1]西南电力设计院,成都610021 [2]中国电力工程顾问集团公司,北京100120 [3]广东电力设计研究院,广州510663 [4]中南电力设计院,武汉430071

出  处:《南方电网技术》2011年第6期51-54,113,共5页Southern Power System Technology

摘  要:根据"十二五"期间云南西电东送容量规划,综合考虑送端外送电能力、受端电网承受能力、输电通道经济性以及电网安全性等,研究了"十二五"期间云南给南方电网送电曲线。结果显示,云南向广东的送电规模最大达到18.50 GW,送电量5年累计为286.6 TWh;云南向广西的送电规模最大达到3 GW,送电量3年累计为31.7 TWh;云南向广东送电曲线、向广西送电曲线的输电小时合理范围分别为3 800~5 000 h和3 600~4 800 h。On the basis of electric power transmission capacity planning form west to east during the "12th Five-Year" period,the power transmission curve form Yunnan to CSG is studied and proposed with considering generating capacity of sending power grid,receptivity of received power grid,economical efficiency of transmission equipments and security of power system.Results showed that the maximum scale of power transmission from Yunnan to Guangdong would reach 18.50 GW;electricity would accumulate 286.6 TWh in five years;reasonable transmission equipment availability hour would be between 3 800 h and 5 000 h.Results also showed that from Yunnan to Guangxi,the maximum scale of power transmission would reach 3 GW;electricity would accumulate 31.7 TWh in three years;reasonable transmission equipment availability hour would be between 3 600 h and 4 800 h.

关 键 词:云南电力 水力发电 送电曲线 西电东送 送电规模 电力系统规划 

分 类 号:TM715[电气工程—电力系统及自动化]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象