高拱坝泄洪水垫塘衬砌稳定性研究  被引量:5

Study on Plunge Pool Concrete Lifting Stability for Flood Dischare of a High Arch Dam

在线阅读下载全文

作  者:杨永全[1] 戴光清[1] 张建民[1] 

机构地区:[1]四川大学高速水力学国家重点实验室,四川成都610065

出  处:《云南水力发电》2000年第2期22-25,共4页Yunnan Water Power

基  金:"九五"国家科技攻关项目子题!(96-221-05-01-02)

摘  要:对窄河谷、高拱坝、大流量坝身泄洪挑流消能水垫塘的防冲安全及其混凝土衬砌优化设计问题作了全面研究,结合小湾工程采用局部水工模型试验研究了小湾工程水垫塘衬砌块的抗冲稳定性,提出了应用瞬交流和震荡流理论研究衬砌冲刷破坏机理、建立新的设计模式的新概念,讨论了水垫塘衬砌设计模式的有关问题,并对该工程的设计提出了具体建议。This paper made an overall study on the erosion control of a plunge pool for dam body flood discharge trajectory energy dissipation in the case of a narrow valley, a high arch dam and a large discharge, and its concrete lining optimization design. The application of the theories of transient flow and oscillating flow was advanced to study the mechanism of scouring damage of the plunge pool lining, and to form a new design mode concept based on the study of the scouring - resistant stability of the plunge pool concrete lining blocks using the hydraulic model test for the Xiaowan hydropower project. The paper also discussed some problems relating to the design mode of the plunge pool concrete lining and offered some specific suggestions on the design of the plunge pool concrete lining for the Xiaowan project.

关 键 词:小湾水电站 挑流消能 水垫塘抗冲稳定 衬砌设计 

分 类 号:TV653[水利工程—水利水电工程] TV7

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象