机构地区:[1]汉江水电开发有限责任公司,湖北十堰442200 [2]汉江水利水电(集团)有限责任公司发展计划部,湖北丹江口442700
出 处:《人民长江》2012年第16期54-58,共5页Yangtze River
摘 要:潘口水电站筑坝材料繁多,主堆石区又是采用两种料源互层填筑,给大坝填筑施工带来很大难度。根据施工总进度计划,大坝填筑共分Ⅵ期进行,采用进占法施工,遵循"先粗后细、全断面均匀上升"的原则,各道工序流水作业,各区之间标识明显。施工质量控制采取以过程控制为主、现场检查为辅的双控措施。对施工措施和质量保证措施作了详细介绍,可供同类工程参考。The different features of numerous dam materials bring about large difficulties for filling construction of Pankou hy- dropower station which only uses 2 kinds of materials for embedded layers at main rockfill area. According to the construction schedule, the dam is filled in VI phases with advance - filling method and by the principle of " rough materials first, uniform rise of the whole section". The filling construction is carried out with the line production for each procedure with the obvious identifi- cation of each filling section. The in - site sampling and the construction process control (main measure) are adopted to ensure the construction quality. The construction and quality assurance measures are described in detail to provide the reference for simi- lar projects.
分 类 号:TV631.4[水利工程—水利水电工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.249