大跨度多段箱形梁安装施工技术  被引量:3

CONSTRUCTION TECHNIQUE FOR INSTALLATION OF WIDE-SPAN MULTI-SECTION BOX BEAM

在线阅读下载全文

作  者:田佳森 邢国荣[1] 安恺[1] 

机构地区:[1]北京建工集团有限责任公司,北京100055

出  处:《建筑技术》2012年第11期997-1000,共4页Architecture Technology

摘  要:中国人寿研发中心F-05地块(数据中心)工程通廊箱形梁长度为27m,单根重21t,由于受现场条件限制,将钢梁分为6段安装。时值冬期施工,受风、温度影响大。通过合理安排焊接时间、合理安排焊接顺序、搭设防风棚、焊接前预热、增加连接板等措施,确保了分段安装构件的质量。China Life Center F-05 Block ( Data Center ) project adopts corridor box beam whose total length is 27m and weight of each piece is 21t. Due to limitation of field conditions, the steel beam is divided into 6 parts. The construction is carried out in winter, suffering severe wind and temperature influences. Installation quality of multi-section members are successfully ensured through adoption of various measures, such as reasonable arrangement of welding time and welding sequence, erection of windproof shed, pre-heating before welding and addition of connecting plates, etc.

关 键 词:钢结构 大跨度 冬期施工 焊接 焊缝 

分 类 号:TU758[建筑科学—建筑技术科学]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象