机构地区:[1]淮北徐楼矿业有限公司,安徽淮北市235100 [2]长沙矿山研究院有限责任公司,湖南长沙410012
出 处:《矿业研究与开发》2012年第6期101-104,109,共5页Mining Research and Development
摘 要:针对某铁矿二期工程采矿范围内的水文地质条件和矿井充水因素及以往报告中该铁矿二期工程采矿范围内的矿坑涌水量预测值进行了分析,基于该矿一期工程帷幕注浆的堵水率和解析法分别预测了该铁矿二期工程实施帷幕注浆工程以后的矿坑涌水量。综合预测结果为:二期帷幕工程以后的正常矿坑涌水量为20093 m3/d,二期帷幕工程以后最大矿坑涌水量为31212.7 m3/d。根据预测结果和矿山实际情况,提出了一些建议。This paper analyzes the hydro - geological conditions, water filling factors and the predicted mine water inflow values given in the past reports within the mining area in the second phase mining of some iron mine. Based on the water shutoff rate of curtain grouting in the first phase mining and analytic method, the mine water inflow in the second phase mining after imple- menting curtain grouting is predicted. The comprehensive prediction result is that the normal mine water inflow is 20093 m^3/d, maximum mine water inflow is 31212. 7 m^3/d in the second phase mining of the iron mine after curtain grouting. Finally, according to the predicted results and actual conditions of the mine, some suggestions are put forward.
分 类 号:TD742.1[矿业工程—矿井通风与安全]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:3.139.239.109