极复杂条件下6.5m大采高工作面综采技术研究  被引量:8

Study on 6.5m High Cutting Fully Mechanized Coal Mining Technology under Ultra Complicated Conditions

在线阅读下载全文

作  者:王德胜[1] 潘卫东[2] 

机构地区:[1]冀中能源股份有限公司东庞矿,河北邢台054201 [2]中国矿业大学(北京)资源与安全工程学院,北京100083

出  处:《煤炭工程》2013年第1期52-53,56,共3页Coal Engineering

基  金:国家自然科学基金资助项目(51004109);北京市教委科技资助项目(km201110853006);中央高校基本科研业务费专项资金资助(2010QZ02)

摘  要:以东庞煤矿为工程背景,针对极复杂煤层起伏变化大、倾角大等技术难点,主要运用了理论分析和技术比较的方法,研究了2612大采高工作面的开采技术和工艺。结果表明:通过机电设备改造和更改拉架顺序等措施,有效解决了大角度俯采过程中存在的问题;合理的注浆加固措施控制住了大采高工作面仰采过程中的煤壁片帮和冒顶。Taking Dongoang Mine as a engineering background, according to a high wavy variation of the ultra complicated seam, high inclination and other technical problems, a theoretical analysis and a technical comparison method were applied to study the mining technology and technique of No. 2612 high cutting coal mining face. The results showed that with the reconstruction of the electromechanic equipment, the change of the powered support advancing sequence and other measures, the problems existed in the high inclined bending mining process were effectively solved. The rational grouting reinforcement measures could control the coal spalling and roof falling during the bending operation process of the high cutting coal mining face.

关 键 词:复杂地质条件 大采高工作面 煤壁片帮 化学注浆 

分 类 号:TD823.253[矿业工程—煤矿开采]

 