灵乡铁矿残留点柱回收与采空区稳定性分析  被引量:6

Analysis on Recovery of Residual Point Pillars and Stability of Mined-out Areas in Lingxiang Iron Mine

在线阅读下载全文

作  者:王纪鹏[1] 欧阳治华[1] 刘夏临[1] 李苗[1] 

机构地区:[1]武汉科技大学资源与环境工程学院

出  处:《金属矿山》2013年第1期15-19,共5页Metal Mine

摘  要:针对灵乡铁矿拟回采采空区内部分点柱对空区上覆岩层和地表设施的影响,采用有限元法对其回采过程进行了模拟,揭示了回采过程中点柱的应力变化规律及顶板的应力分布变化,证明了回采工作的可行性。结合回采过程中应力变化,建议采用方案二进行回采是比较安全的,同时建议在2号、5号点柱上布置声发射监测点。In view of the influence of the recovery of residual point pillars at mined-out areas on the overlying strata and surface facilities in Lingxiang Iron Mine, the stoping process of the residual point pillars were simulated with FEM, indi- cating the stress change law and stress distribution of roof and verifying the feasibility of the recovery. According to the stress variety in the stoping process,it is recommended that the second stoping scheme be a lot safer and AE monitoring points be laid out at No. 2 and No. 5 pillars.

关 键 词:采空区 点柱回收 数值模拟 声发射监测 

分 类 号:TD752.2[矿业工程—矿井通风与安全]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象