转角塔主角钢插入式基础预偏数据几何修正法  

Geometric Correction Method of Deviation Data for Inserted-type Angle Steel Foundation of Corner Tower

在线阅读下载全文

作  者:张教臣 

机构地区:[1]四川电力建设公司,四川成都610000

出  处:《水电能源科学》2013年第1期177-179,共3页Water Resources and Power

摘  要:为解决转角塔在铁塔组立后插入角钢与铁塔接腿角钢连接处出现塌腰或鼓肚的现象,结合实际工程与施工经验,提出了预偏数据几何修正法,对预偏值的取值和基础根开、角钢根开、主角钢坡度调整的计算进行了分析和修正。通过与基础设计数据的对比表明,几何修正法使铁塔的基础施工数据得到了合理的调整、使铁塔和基础达到了设计的预偏效果,并确保了铁塔整体及局部受力的合理与稳定。In order to solve the bulging phenomenon in joints of inserted angle steel and iron tower legs angle steel af- ter assembly of tower, this paper proposes geometric correction method of deviation data by combining with the actual en- gineering and previous construction experience. The deviation value, foot distance of base, foot distance of angle steel, adjustment of main angle steel slope are calculated and analyzed. Comparison of design data, geometric correction method adjusts the foundation construction data of tower reasonably, which makes the design of tower and foundation attaining the deviation effect. Therefore, it ensures the force stability and rationality of the tower.

关 键 词:转角塔 主角钢插入式基础 预偏 几何修正法 全方位不等高 

分 类 号:TM754[电气工程—电力系统及自动化]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象