217吨吊钩上下模铸造工艺的研究  被引量:1

Study on Casting Process for Upper and Lower Die of 217 Ton Hook

在线阅读下载全文

作  者:孙振国[1] 王话[1] 康文[1] 李晓明[1] 杨洪洲[1] 刘洪生[1] 贺杨[1] 孙爱新[1] 

机构地区:[1]沈阳铸锻工业有限公司铸钢公司,辽宁沈阳110142

出  处:《铸造》2013年第1期71-72,共2页Foundry

摘  要:217吨吊钩上下模是生产天车双钩钩头的重要模具,属于厚壁铸件,在使用过程中承受高温及巨大载荷,因此对其性能要求非常高。本文通过对轮廓尺寸2 120 mm×1 760 mm×500 mm,材质为ZG310-570,主体壁厚500 mm的吊钩上下模进行结构分析,针对制造难点,设计出符合实际生产情况的铸造工艺,并成功地铸造出吊钩上下模铸件。The upper and lower dies of 217 ton hook are important dies for producing the double hook of crane, belonging to thick wall casting, which bear high temperature and huge load when being used, so the property requirements are very high. The structures of the upper and lower dies of hook with outline dimension 2 120 mm×1 760 mm×500 mm, ZG310-570 and main wall thickness 500 mm, were analyzed in the paper. Casting process toward manufacturing difficulty was designed according to conditions of the company. The upper and lower dies of hook were produced successfully.

关 键 词:吊钩上下模 厚壁铸件 制造难点 铸造工艺 

分 类 号:TG24[金属学及工艺—铸造]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象