机构地区:[1]华北水利水电学院,河南郑州450011 [2]郑州市水利建筑勘测设计院,河南郑州450007 [3]桐柏县水利局,河南桐柏474750
出 处:《人民黄河》2013年第2期103-104,共2页Yellow River
摘 要:为确保南水北调中线工程总干渠在穿越掏砂洞时能够安全稳定的运行,对掏砂洞进行了灌浆处理。基于现场勘察试验资料,采用三维有限元对代表性渠段在多种工况下进行应力与变形计算分析。结果表明:经过水泥黏土浆灌浆处理后,总干渠护砌在穿越掏砂洞上方时,应力与变形均满足设计要求。In order to ensure the safe and stable operation of crossing the dig sand hole of the main canal of South-to-North Water Diversion Middle Route Project, the grouting treatment measures were taken to deal with dig sand hole. Based on field survey test data, by three dimensional finite element method, stress and deformation of representative channel sections in a variety of conditions were computed and analyzed. The results show that, after cement clay slurry grouting treatment, the stress and deformation of main canal embankment across dig sand holes meet the design requirements.
分 类 号:TV672[水利工程—水利水电工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.3