基于模糊集合分析法与圆形分布法的水库汛期分期研究  被引量:9

Study on Flood Season Staging Based on Fuzzy Set Analysis Method and Circle Distribution Method

在线阅读下载全文

作  者:郭金城 郭倩 武学毅[3] 

机构地区:[1]通辽市西辽河枢纽工程管理处,内蒙古通辽028000 [2]中国水利工程协会,北京100055 [3]中国水利水电科学研究院,北京100038

出  处:《水电能源科学》2013年第3期50-53,共4页Water Resources and Power

摘  要:为研究水库汛期分期基本原则,以构皮滩水库控制流域洪水为例,分别采用模糊集合分析法和圆形分布法研究了水库汛期分期问题。模糊集合分析法确定的主汛期为6月28日~8月7日;圆形分布法确定的主汛期不考虑洪水量级为6月2日~8月12日,考虑洪水量级为6月4日~8月5日;后者考虑了个别出现时间较早洪水,偏保守,且洪水取样时段对主汛期划分影响较小,洪水取样量级对主汛期划分有一定影响。水库入汛判断标准宜以模糊集合分析法为基础,汛期分期宜以圆形分布法为准。For the purpose of research on the principle of flood season staging, the fuzzy set analysis method and the circle distribution method were used to calculate the flood season of Goupitan reservoir. The results show that the main flood season based the calculation of fuzzy set analysis were June 28 to August 7 ; the main flood season based the calcula- tion of circle distribution method were June 2 to August 12 with not considering flood magnitude, and June 4 to August 5 with considering flood magnitude; the circle distribution method was conservative because it considered the individual ab- normal flood date. The sampling period of samples less defected the flood season staging and the flood magnitude of sam- ples defected the flood season staging certainly. It is better that the beginning and ending of the flood should be defined by using fuzzy set analysis method and the flood season should be staged by circle distribution method.

关 键 词:洪水资源 汛期分期 模糊集合分析法 圆形分布法 构皮滩水库 

分 类 号:TV697.1[水利工程—水利水电工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象