潘口水库调蓄作用对黄龙滩大坝的防洪安全影响  被引量:4

Impact of Pankou Reservoir Operation on Flood Control Safety of Huanglongtan Dam

在线阅读下载全文

作  者:梁犁丽[1] 袁林山[2] 胡宇丰[1] 顾绍峰[2] 张云辉[1] 郭正云[2] 

机构地区:[1]中国水利水电科学研究院,北京100038 [2]湖北黄龙滩水力发电厂,湖北十堰442005

出  处:《水电能源科学》2013年第3期58-61,231,共5页Water Resources and Power

基  金:南京水利科学研究院水文水资源与水利工程科学国家重点实验室开放研究基金资助项目(2011491911);国家自然科学基金资助项目(51209223;51079160)

摘  要:针对潘口水库正常蓄水运行后将对黄龙滩大坝防洪安全产生极大影响的问题,利用龙格—库塔数值解法编制了水库洪水调算程序,采用有无对比法研究了有、无潘口水电站时黄龙滩大坝的防洪安全。结果表明,黄龙滩水库洪水调度方式由常规调度调整为预泄调度时,潘口水库的蓄水运行可大幅降低坝前水位、延迟洪峰和最高水位出现时间,大坝防洪标准将提高到2 000年一遇。Operating as a controlling reservoir, Pankou reservoir is located in the upstream of Huanglongtan dam, which will have a great impact on the flood control safety of Huanglongtan dam. In this paper, using the method of with and without comparison, taking advantage of the Runge-Kutta numerical solution, it programs the reservoir flood regula- tion programmes and researches the flood control safety of Huanglongtan dam with and without Pankou reservoir. The re- sults show that when the Huanglongtan reservoir flood regulation changing from the conventional scheduling to pre-dis- charge scheduling, the operation of Pankou reservoir can significantly reduce the water level before the dam, and delay the occurrence time of flood peak and the highest water level, then the recurrence period of flood will be raised to 2 000 years.

关 键 词:洪水调度 有无对比法 龙格—库塔数值解法 潘口水库 黄龙滩水库 

分 类 号:TV697.1[水利工程—水利水电工程]

 