亭子口水利枢纽三期下游全年围堰设计与施工  被引量:1

Design and Construction of Downstream All-year Cofferdam for the Phase-III Diversion of Tingzikou Water Control Project

在线阅读下载全文

作  者:孔令富[1] 

机构地区:[1]中国水利水电第七工程局有限公司,四川成都610081

出  处:《水力发电》2013年第6期84-85,88,共3页Water Power

摘  要:亭子口水利枢纽工程三期下游全年围堰在三期上下游枯水期围堰的围护下,具有干地施工的特殊条件。结合现场实际情况,对围堰施工方案进行了优化,在汛前提前进行了枯水期常水位以下围堰心墙施工,使得汛后水位下降、混凝土心墙外露后即可展开基坑抽水和开挖工作,达到了加快施工进度和减小围堰填筑料挖运成本的目的。Under the protection of phase-HI upstream and downstream dry-season cofferdams, the downstream phase-III allyear cofferdam in Tingzikou Water Control Project can be constructed in dry environment. Based on the actual condition, the construction method of downstream phase-III all-year cofferdam is optimized. The pouring of cofferdam concrete core wall below normal low-water level is completed in dry season, and after flood season, the pumping of pit and the excavation of pit foundation is immediately conducted when the water level is below than the top of core wall. The construction method of phase-III all-year cofferdam can speed up the construction and saves the costs on cofferdam filling material excavation and transportation.

关 键 词:三期围堰 混凝土心墙 设计 施工 亭子口水利枢纽工程 

分 类 号:TV551[水利工程—水利水电工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象