峡江水利枢纽工程二期枯水1号围堰改线方案研究  被引量:3

Study on Change Line Scheme for the No.1 Cofferdam in Dry Season in Xiajiang Hydro-junction Stage 2 Project

在线阅读下载全文

作  者:黄志文[1] 王军辉[1] 贾群超[1] 

机构地区:[1]武警水电第二总队五支队,江苏常州213135

出  处:《施工技术》2013年第12期54-56,共3页Construction Technology

摘  要:江西省峡江水利枢纽工程主体土建Ⅲ标工程由于船闸特大断层、泄水闸断层等不良地质条件影响,开挖工程量和开挖难度大大增加,导致该阶段围堰防护的施工工期严重滞后。为了给工程争取1个月的施工时间,根据区域水文气象条件和赣江水情,通过将原有的二期枯水1号围堰改线并与三期混凝土纵向围堰相接,提高堰顶高程等措施,达到增加河床过流断面,提高度汛标准,工程实现了安全度汛。The third bidding segment of the civil engineering in Xiajiang Hydro-junction project is added very much in quantities and difficulty of excavation.So construction of the cofferdam in this stage lags behind schedule.To win the project construction time of a month,based on hydro-meteorological condition and Ganjiang river water level,by changing the no.1 cofferdam's line,connecting the cofferdam with longitudinal concrete cofferdam in stage 3 and improving elevation of the cofferdam top,the flowing section of the river can be increased to ensure the project can be constructed safely.

关 键 词:水利枢纽工程 围堰 施工工期 改线 度汛 

分 类 号:TV6[水利工程—水利水电工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象