溪洛渡深孔弧门充压水封运用预控措施研究  被引量:6

Study on Pre-control Measures of Pressurized Water Seal for the Bottom Outlet Radial Gates of XiluoduHydropower Station

在线阅读下载全文

作  者:席前伟 贾鑫 

机构地区:[1]溪洛渡水力发电厂,云南永善657300

出  处:《水力发电》2013年第8期33-35,49,共4页Water Power

摘  要:溪洛渡深孔弧门采用常规预压缩水封和充压水封两套水封止水。深孔充压水封在充分吸取其他工程成功经验的基础上,分别考虑设计和选型、安装调试、运行管理3个阶段,提前制定了符合自身特点的预控措施。目前,充压水封处于初期投运阶段,前两阶段取得了良好的效果。后续运行过程中,还将重点关注控制程序是否适应各种工况,不断完善系统的工作性能。The conventional pre-compressed water seal and the pressurized water seal are simultaneously used in water sealing of bottom outlet radial gates in Xiluodu Hydropower Station. The pre-control measures for pressurized water seals are specially developed in advance for three stages of design and type selection, installation and commissioning, as well as operation and management after learning lessons from other hydropower projects. Currently, the pressurized water seals are commissioning and achieve good results. In following operation, it is focused on the control program whether adapting various operating conditions and to improve system performance continuously.

关 键 词:充压水封 深孔弧门 溪洛渡水电站 

分 类 号:TV663.2[水利工程—水利水电工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象