某钢-木混合结构拔柱设计与施工全过程监控技术  被引量:1

Design and Whole Construction Process Monitoring of a Steel-timber Composite Structure for Removing Columns

在线阅读下载全文

作  者:李密[1] 姜浩[1] 郑昊[1] 

机构地区:[1]上海市建筑科学研究院上海市工程结构新技术重点实验室,上海200032

出  处:《施工技术》2013年第16期16-18,共3页Construction Technology

基  金:"十二五"国家科技支撑计划课题:典型气候地区既有居住建筑绿色化改造技术研究与工程示范(2012BAJ06B02)

摘  要:某钢-木混合结构的老建筑1~2层为铸铁柱、钢梁结构,3~5层为木结构木格栅楼面,梁柱节点均为铰接设计。采用整浇刚性节点将1层4根铸铁柱拔除,并对施工进行全过程监控。结果表明新增托梁应变、挠度均较小,拔柱前后周边钢柱无新增倾斜及不均匀沉降,该设计方案及施工控制合理可行。An old building with cast iron column and steel beams in the first and second floor,timber structure and wooden grids from the third floor to fifth floor is designed by hinged joint details of beams and columns.The method of integral pouring rigid joint is adopted to remove four columns in the first floor with whole construction process monitoring,which shows that the strain and deflection of the new supporting beam is low and the inclination and uneven settlement of the steel columns remains almost no changes before and after the construction of supporting beam and removing column,and it is reasonable and feasible for the design and construction monitoring.

关 键 词:加固 改造 托梁拔柱 监测 

分 类 号:TU391[建筑科学—结构工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象