向塘西编组站扩能改造施工过渡方案分析  被引量:1

Research on Transitional Plan for Capacity Improvement of Xiangtangxi Marshalling Station

在线阅读下载全文

作  者:侯香菊[1] 汪强[1] 

机构地区:[1]中铁二院工程集团有限责任公司,成都610031

出  处:《高速铁路技术》2013年第5期35-38,共4页High Speed Railway Technology

摘  要:向塘西编组站为路网性编组站。扩能改造工程需将既有混合式二级七场站型改扩建为纵向三级八场站型。因改建既有设备较多,对既有运营有较大的干扰。文章根据车流特点和运输生产需求,合理安排施工期间的车场和线路分配使用情况,详细分析了先实施上行系统、后实施下行系统并分场逐步实施的施工过渡方案。分析结果证明该扩能方案既可在有限的场地条件下满足运输生产的要求,又能确保设计方案顺利实施,避免了施工过渡便线,减少过渡工程。且在实施中贯穿了改建设计方案与施工过渡方案一体化设计的理念,对既有线大型车站设计方案与施工过渡方案的系统性设计具有很好的借鉴。Xiangtangxi marshalling station is a railway network marshalling station. Its capacity improvement project needs to make its existing two-stage-seven-yard into three-stage-eight-yard, where there are great many existing facilities to be improved and larger interference to the existing operation. Based on traffic flow characteristics and transportation demands, yard's reasonable arrangement during construction and track allocation and occupation, The detailed analysis has been made of the transitional plan for constructing the upgoing system firstly, then downgoing system and construc- ting the yard gradually and separately. The results has proved that such construction transitional plan can satisfy the re- quirements of transportation production in the restricted conditions of site, ensure the successful implementation of design plan, avoids the temporary line for building transition setcion, reduces transitional project, furthermore carry out the the- ory of integrating design and construction into one, and is a good example for other existing station design and construc- tion transitional plan.

关 键 词:向塘西 编组站 施工过渡 扩能改造工程 

分 类 号:U291.41[交通运输工程—交通运输规划与管理]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象