系杆拱桥吊杆更换工序优化研究  被引量:1

Study on Optimization of Suspender Replacement Process for Tied Arch Bridge

在线阅读下载全文

作  者:黄永辉[1] 王春龙 

机构地区:[1]广州大学广州大学-淡江大学工程结构灾害与控制联合研究中心,广东广州510006 [2]广东省公路工程质量监测中心,广东广州510500

出  处:《施工技术》2013年第23期25-29,共5页Construction Technology

基  金:广东省自然科学基金项目(S2012040007317);广东省科技计划项目(2010A040308005);广东高校优秀青年创新人才培养计划项目(2012LYM_0101)

摘  要:对系杆拱桥吊杆更换过程进行了详细计算,对比分析了等步长更换吊杆和变步长更换吊杆两种施工方法,结果表明,变步长方法比等步长方法更为安全,尤其对于旧吊杆病害较多、锚头锈蚀严重的情况。根据背景桥梁的实际情况,提出使用变步长张拉临时吊杆和割断相应钢丝的方法。In this paper, the suspender replacement process of tied arch bridge is calculated in detail. Suspender replacement methods with equal step and variable step size are comparatively studied. The result shows that the replacement method with variable step size is safer than the replacement method with equal step size especially for the suspenders with many diseases and the anchor head seriously corroded. According to the actual situation of the bridge in the background, the authors put forward the replacement method with variable step size in the bridge reinforcement project.

关 键 词:桥梁工程 系杆拱桥 吊杆更换 优化 

分 类 号:U448.225[建筑科学—桥梁与隧道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象