溪洛渡水电站左岸主厂房下游侧墙7#机变形问题探讨  

Discussion on 7# Machine Side Wall Deformation of Downstream Left Bank Powerhouse Station in Xiluodu Hydropower

在线阅读下载全文

作  者:刘懿辉[1] 李思嘉[1] 吴灌洲[1] 

机构地区:[1]中国水电顾问集团成都勘测设计研究院,成都610072

出  处:《黑龙江水利科技》2013年第11期29-32,共4页Heilongjiang Hydraulic Science and Technology

摘  要:溪洛渡水电站位于四川省雷波县和云南省永善县境内金沙江干流,为中国第二大水电工程。通过介绍溪洛渡水电站左岸主厂房在开挖过程中围岩变形状况,结合厂房围岩地质条件、监测数据及声波资料,对相互间影响关系进行分析,针对松弛、变形部位进行加固处理。Xiluodu hydropower station is located in the territory of Sichuan Province, Leibo county and the Yunnan province Yongshan County, the main stream of Jinsha River, China "s second largest hydropower project. Based on the deformation conditions of the surrounding rock in the process of excavation of the main plant on the left bank in Xiluodu hydropower station, combined with geological conditions, monitoring data and acoustic data of the powerhouse, the relationships of them were analyzed, and the flabby and deformed parts were reinforced.

关 键 词:围岩变形 松弛 监测分析 加固措施 

分 类 号:U456.31[建筑科学—桥梁与隧道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象