机构地区:[1]中国市政工程华北设计研究总院,天津300074
出 处:《中国给水排水》2014年第4期57-59,共3页China Water & Wastewater
基 金:国家水体污染控制与治理科技重大专项(2012ZX07308-001)
摘 要:某污水处理项目包括2座3 500 m3/d的集成式污水处理站、1座2 000 m3/d的污水提升泵站及配套管道工程,总投资约3 600万元。该工程采用混凝沉淀/氧化沟/MBR组合工艺,出水经紫外消毒后就近排入景观河道。介绍了工艺流程、设计参数、设备配置、调试运行情况等。调试运行期间出水COD<50 mg/L、SS<1 mg/L、NH3-N<3 mg/L、TP<0.3 mg/L,满足设计要求。A sewage treatment project with total engineering investment of 36 million yuan includes two integrated sewage treatment stations with the design capacity of 3 500 m3/d, a lift pumping station with the design capacity of 2 000 m3/d and sewage pipeline. With coagulation sedimentation, oxidation ditch and MBR combination process treatment, the effluent after ultraviolet disinfection drained into the nearest landscape river. The process flow, design parameters, equipment allocation and commissioning operation were introduced. The commissioning operation results showed that the effluent concentrations of COD, SS, NH3 - N and TP were below 50 mg/L, 1 mg/L, 3 mg/L and 0.3 mg/L, and the design requirement was met.
分 类 号:X703[环境科学与工程—环境工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:18.223.114.251