检索规则说明:AND代表“并且”;OR代表“或者”;NOT代表“不包含”;(注意必须大写,运算符两边需空一格)
检 索 范 例 :范例一: (K=图书馆学 OR K=情报学) AND A=范并思 范例二:J=计算机应用与软件 AND (U=C++ OR U=Basic) NOT M=Visual
出 处:《建筑电气》2014年第2期50-55,共6页Building Electricity
基 金:广州市气象局科研项目;项目名称:人工接地装置的设计研究
摘 要:结合某110 kV变电站接地装置工程的实践,对该站所处的环境情况、气象资料、土质和土壤状况等进行实地勘测,考虑接地电阻、接触电位差和跨步电位差应满足的要求,对该站接地装置进行设计。通过对比采取措施前后接地电阻的大小,选取结合深斜井的降阻设计方案,得到符合要求的电阻值,从而论证接地电阻改善方法的有效性和可行性。Based on the practice of a earth-termination system project at a 110 kV transformer substation, field investigation on the environment condition, meteorological data, soil quality and soil condition in the said substation are conducted; the earth-termination system is designed considering the requirements for the earthing resistance, contact potential difference and step potential difference. Measures are taken to compare the earthing resistances before and after the improvement, and a resistance reduction design scheme characterized by deep-deviated wells combination is chosen to acquire corresponding resistances meeting the requirements, so as to demonstrate the effectiveness and feasibility of the earthing resistance improvement method.
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.85