施工阶段钢筋砼地下粮食筒仓仓壁受力分析  被引量:2

Wall Stress Analysis of Reinforced Concrete Underground Grain Silos in Construction Stage

在线阅读下载全文

作  者:贾腾南 王振清[1] 丁永刚[1] 

机构地区:[1]河南工业大学土木建筑学院,郑州450001

出  处:《河南科学》2014年第2期216-219,共4页Henan Science

基  金:"十二五"国家科技支撑计划(2011BAD03B00)

摘  要:钢筋混凝土地下圆形粮食筒仓在施工过程中会出现只有仓底板和仓壁,而没有仓顶板的情况.利用有限单元法,分析了此种情况仓壁环向力、径向位移和竖向弯矩的大小以及分布情况.根据计算结果与使用阶段情况的对比,发现这种工况下仓壁拉应力峰值会增大,且最大压应力出现位置会向仓底移动,影响结构安全.实际工程设计时需要对结构认真复核.Reinforced concrete circular underground grain silo maybe only have the floor and wall,without roof in the process of construction. Finite element method was used to analyze silo wall ring force,radial displacement and the size and distribution of vertical bending moment. According to the contrast between calculated results and the condition of using phase,it was found that the maximum tensile stress of silo wall under this condition will increases,and maximum compressive stress location will move to the silo bottom,effecting the safety of the structure. It was suggested to review structure carefully in actual engineering design.

关 键 词:地下粮仓 有限元分析 空间受力 仓壁 仓底板 

分 类 号:TU33[建筑科学—结构工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象