董箐水电站垫层钢管的设计研究  

Design of Cushion Course Steel Pipe in Dongqing Hydropower Station

在线阅读下载全文

作  者:申显柱 李水生[1] 湛正刚[1] 

机构地区:[1]贵阳勘测设计研究院,贵州贵阳550081

出  处:《电力勘测设计》2014年第1期72-76,共5页Electric Power Survey & Design

摘  要:水电站引水钢管末端与发电厂房蜗壳连接处存在变形应力协调问题,董箐引水钢管设计中,采用垫层钢管取代波纹管伸缩节,并进行了分析、计算研究,验证了垫层钢管能适应变形应力协调,具备伸缩节类似功能,且该结构型式可降低施工难度、缩短工期、节省工程投资,具有良好的推广应用价值。The joint between the end of penstock and spiral case is under deformation stress. In Dongqing hydropower project penstock with cushion course was used to take place of bellows expansion joint and related analysis and calculation were carried out. It was proved that penstock with cushion course could handle stress deformation, a function similar to joints. This way can make construction easier, shorten construction period and save investment. It's worthy of being promoted.

关 键 词:引水钢管 垫层钢管 伸缩节 应力变形 董箐水电站 

分 类 号:TM612[电气工程—电力系统及自动化]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象