大型泥水盾构推进遇未探明群桩的分析及处理  

An Analysis & Treatment of Pushing Large-scale Slurry Shield Running into Unverified Pile Group

在线阅读下载全文

作  者:荣建 

机构地区:[1]上海城建市政工程(集团)有限公司,上海200065

出  处:《中国市政工程》2014年第2期70-72,111,共3页China Municipal Engineering

摘  要:上海仙霞西路隧道工程北线泥水盾构推进遇到未探明的南陈巷周家浜桥桥桩,阐述遇桥桩的经过及盾构机切削部分桩体后参数的改变。通过处理方案的比选,采用套管法将桩基拔除的方案,拔除施工期间采取措施防止盾构下沉和周边土体的变形。桩基拔除后盾构顺利穿越桥桩影响区域。Taking Shanghai West Xianxia Rd. tunnel project for example, its north line slurry shield has run into unverified pile group of Nanchenxiang Zhoujiabang Bridge during the pushing process. The paper describes the procedure of running into bridge piles and the parameters change of shield machine cutting partial pile body. Through the selection and comparison of treatment plans, the plan of pipe in pipe method to pull out pile foundation is adopted finally. During the pulling out construction period, measures are used to prevent shield settlement and surrounding soil body deformation, and the shield can cross the area infl uenced by bridge piles successfully after pulling out these pile foundations.

关 键 词:泥水盾构 未探明群桩 桩基拔除 

分 类 号:U455.43[建筑科学—桥梁与隧道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象