深部岩体群洞开挖顺序对围岩稳定性影响分析  

Analysis on the Long-term Stability of Porous Deep Tunnel Excavation with Different Sequence

在线阅读下载全文

作  者:李兴权[1] 

机构地区:[1]承德石油高等专科学校,河北承德067000

出  处:《科技视界》2014年第6期212-213,共2页Science & Technology Vision

摘  要:针对多孔隧洞围岩开挖的长期稳定性,以锦屏二级水电站引水隧洞为工程背景,对三种不同的开挖工况进行模拟分析,研究多孔隧洞开挖顺序对围岩长期稳定性的影响。得到了洞室间隔开挖,应力集中范围较小,发生滞后岩爆等围岩变形破坏的可能性小,因此,对于多洞隧道开挖采用间隔开挖法有利于降低滞后岩爆的风险。In order to research the long-term stability of the multi-chamber's excavation, Jinping II Hydropower Station's diversion tunnel as the background, three different excavation conditions are simulated and analyzed to study long-term stability of the porous tunnel excavation with different sequence. The range of stress concentration is a small area. The possibility of delayed rock-burst is very little. Therefore,the risk of delayed rock-burst can be reduced with bay excavation sequence for the porous tunnel.

关 键 词:群洞开挖 深部岩体 数值模拟 滞后岩爆 

分 类 号:TV731.6[水利工程—水利水电工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象