大跨预应力混凝土系梁浇注过程中满堂支架验算  

Scaffoldings Calculation in Large Span Prestressed Concrete Beam Casting

在线阅读下载全文

作  者:史义博[1] 

机构地区:[1]中国中元国际工程公司,北京100089

出  处:《工程建设与设计》2014年第6期117-119,共3页Construction & Design for Engineering

摘  要:某大跨度预应力混凝土系杆拱桥在施工过程中,由于运梁车需从桥面通过,故上部钢管拱桥需滞后施工。此时,系梁荷载达到4 480t,而上部通过的运梁车自重达1 200t。因此,有必要参考实际施工过程对本项目中满堂支架的强度、刚度、稳定性进行验算并给出施工参考性建议,以保证结构施工的安全性。The construction of the steel arch rib in a long-span pre-stressed concrete arch bridge has to be delayed due to the girder transporting vehicles pas sing through. This leads to the prestressed concrete girder carrying a load of 1200 tons in addition to its self-weight o f4480 tons. Thus, it's necessary to check the strength, stiffness as well as the stability of the scaffoldings used to support the girders, for the purpose to provide a construction suggestion and to ensure the safety during construction.

关 键 词:满堂支架 运梁车 刚度 强度 

分 类 号:U448.35[建筑科学—桥梁与隧道工程] U445.35[交通运输工程—道路与铁道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象