软弱煤层大采高工作面即时回撤技术  被引量:15

Instant Removal Gateway for Large Height Working Face in Soft Coal Seam

在线阅读下载全文

作  者:宋斌[1] 

机构地区:[1]山西晋煤集团赵庄煤业有限责任公司,山西长治046605

出  处:《煤矿安全》2014年第6期136-139,共4页Safety in Coal Mines

基  金:国家自然科学青年基金资助项目(51304115);中国煤炭科工集团有限公司科技创新基金资助项目(2012MS005)

摘  要:针对试验工作面末采期间断层构造复杂、预掘回撤通道贯通对接困难、顶板管理难度大等不利因素,采用即时撤架通道的回撤方案。经过末采期间顶板运移与矿压显现特征的实测分析,选定了合理的停采位置。采用理论分析与计算机模拟分析,制定了撤架通道支护方案。工业性试验表明,与预掘撤架通道相比,即时撤架通道施工周期缩短14 d左右,节约工数262人次;并且撤架通道一次成形,变形量小,不需要二次维护。In view of disadvantages such as complex fault structure during the late mining, the holing- through difficulty of pre -excavation removal gateway and great difficulty of roof control, it is determined to adopt instant equipment removal gateway scheme. With measurement analysis of overlying strata movement characteristics during the late mining, the reasonable stop mining location is established. Theoretical analysis and computer simulation are used to develop a plan for withdraw support scheme. Comparing with the preexcavation removal gateway, the instant galeway shortens construction period of about 14 days, saves 262 labors, and its outline is regular with small deformation without secondary maintenanee.

关 键 词:软弱煤层 大采高工作面 搬家倒面 即时撤架通道 

分 类 号:TD322[矿业工程—矿井建设]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象