安庆长江铁路大桥主桥钢梁边跨合龙施工技术  被引量:12

Construction Techniques for Closure of Side Span Steel Girder of Main Bridge of Anqing Changjiang River Railway Bridge

在线阅读下载全文

作  者:孙健家 

机构地区:[1]宁安铁路有限责任公司,安徽芜湖241000

出  处:《桥梁建设》2014年第3期109-113,共5页Bridge Construction

摘  要:安庆长江铁路大桥主桥为主跨580m的双塔三索面连续钢桁梁斜拉桥,主桁采用空间三片桁架结构,桁高15.0m,节间长14.5m,主桁间距14.0m。主桥共设中跨、边跨2个合龙点,先合龙中跨,再合龙边跨。根据边跨合龙前的钢梁安装架设状态,对主桥边跨合龙特点进行详细分析,制定了各项合龙措施,通过合龙措施的敏感性分析,确定边跨合龙方案为起顶5号墩支座,回落7号墩支座。按照此合龙方案调整合龙口状态,使里程偏差≤2cm,轴线偏差≤1cm,竖向高程偏差≤3cm,顺利实现了边跨无应力合龙。The main bridge of Anqing Changjiang River Railway Bridge is a continuous steel truss girder cable-stayed bridge with double pylons, triple cable planes and with a main span of 580 m. The main trusses of the bridge are composed of three spatial trusses that are 15.0 m in height and have panel length of 14.5 m and truss spacing of 14.0 m. On the main bridge, there were totally two closure points arranged at the central span and side span and the closure of the bridge proceeded from the central span first and side span late. In the light of the erection status of the steel truss girder of the bridge before the closure of the side span, the characteristics of the closure of the side span were analyzed in details and the various measures for the closure were formulated. The sensitivity analysis of the measures was also conducted and it was determined that the scheme for the closure should be that the bearings on the Pier No. 5 were to be jacked up and the bearings on the Pier No. 7 to be jacked down. In compliance with the scheme, the closure gap was adjusted to make the mileage deviation ≤ 2 cm, the axial line deviation ≤ 1 cm and the vertical elevation deviation ≤ 3 cm and finally the unstressed closure of the side span was smoothly realized.

关 键 词:铁路桥 斜拉桥 钢桁梁 合龙措施 敏感性分析 桥梁施工 

分 类 号:U448.27[建筑科学—桥梁与隧道工程] U443.32[交通运输工程—道路与铁道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象