巷道工作面突水淹井治理  被引量:5

Control of Mine Water Inrush and Flooded Occurred in Mine Roadway Heading Face

在线阅读下载全文

作  者:邱显水 林丛丛 

机构地区:[1]山东省煤田地质规划勘察研究院,山东泰安277100 [2]枣矿集团中兴建安公司,山东枣庄272100

出  处:《建井技术》2014年第2期4-5,9,共3页Mine Construction Technology

摘  要:马鞭山铁矿风井巷道掘进中,工作面强突水,突水量800m3/h左右,造成淹井后,采用先排后堵的方案治理,无法达到排水目标。后经专家论证,决定采用先堵后排的方案治理。施工时,从地面向井下巷道施工2个钻孔,分别用于构筑挡水墙和注浆充填封堵。施工后,所形成的挡水墙耐压较好,浆液对导水通道充填封堵较好,达到了预期效果。2013年6月,矿上顺利将矿井水排掉,矿井顺利恢复生产。During a mine roadway heading in a Mine Ventilation Shaft of Mabianshan Iron Mine ,a mine strong water inrush was occurred in the heading face with a water inrush volume about 800m3/h.Thus the mine was flooded ,a control plan of a first water drainage and then water sealing was applied and the water drainage target was hard to be reached.After the expert argumentation conducted ,a control plan of a first water sealing and then water drainage was determined and applied.During the construc-tion ,two boreholes were drilled from the surface ground to the mine roadway in the underground mine and were applied individually to build a water retaining wall and to make the grouting ,backfill and sealing operations.After the construction ,the water retaining wall formed could have good pressure resistances ,the grout could have good backfill and sealing to the water flow channel with the predicted effect.In June ,2013 ,the inrush water in the mine was successfully drained off and the mine was suc-cessfully restored in production.

关 键 词:巷道工作面 突水淹井 先堵后排 挡水墙 钻孔 

分 类 号:TD745.3[矿业工程—矿井通风与安全]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象