珠海电厂700MW机组超速限制系统特性分析  被引量:5

CHARACTERISTICS ANALYSIS TO OVERSPEED LIMITING SYSTEM OF 700MW UNIT AT ZHUHAI POWER PLANT

在线阅读下载全文

作  者:田丰[1] 余天龙[1] 欧坚 王进 吴华盛 

机构地区:[1]广东省电力试验研究所,广州510600 [2]连州发电厂,广东连州5134353 [3]珠海发电厂,广东珠海519050

出  处:《热力发电》2001年第2期46-48,58,共4页Thermal Power Generation

摘  要:结合珠海电厂 2× 70 0MW 1号机组进行的 4级甩负荷试验 ,分析了该机组电超速保护装置(OPC)的设计特性 ,论述了电超速保护回路的设计要求。该机组甩负荷试验结果表明 ,OPC的设计虽然通过若干电子环节 ,但在转速回路中引入功率不平衡的补偿 ,不仅具备汽门快关的功能 。Combined with 4-stage load rejection testing of unit No1 (700MW) at Zhuhai Power Plant, the design characteristics of overspeed limiting system of said unit has been analyzed, the design requirements of the overspeed limiting system discussed, the load rejection testing shows, though a number of electronic loops were designed in the said system, but the power nonequilibrium newly introduced to compensate the speed circuit not only enables the governor valve to be fast closed, but also ensures the system to have good response to load rejection under various load conditions.

关 键 词:大型机组 电超速保护装置 转速控制系统 甩负荷试验 电厂 

分 类 号:TM621.3[电气工程—电力系统及自动化]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象