白云铁矿主采场深深部掘沟工程优化  被引量:2

Engineering Optimization of Trenching Deep Part in Main Stope of Baiyunebo Iron Mine

在线阅读下载全文

作  者:杨霞[1,2] 王创业[1] 梁浩然[2] 

机构地区:[1]内蒙古科技大学矿业工程学院,内蒙古包头010410 [2]包钢(集团)公司白云鄂博铁矿,内蒙古包头014080

出  处:《包钢科技》2014年第5期9-11,26,共4页Science & Technology of Baotou Steel

摘  要:白云铁矿主矿采场现已进入深深部开采,空间狭小,出水量大,严重制约掘沟工程的正常进行。为保证掘沟工程的顺利实施,需要根据现场问题,综合考虑穿孔、排水、采掘等工序流程的合理布设与衔接,以实现掘沟工程的最优化,保证尽早出矿和采场生产的正常持续。The main stope of Baiyunebo Iron Mine is now entering deep mining,narrow space and great hydraulic discharge seriously restrict the normal operations of trenching engineering. In order to guarantee the smooth engineering,the reasonable arrangement and link up of such process flow as perforation,drainage and digging should be considered according to the problems at field so that the engineering could be optimal,the ore removal could be as early as possible and the productions could be normal and continuous.

关 键 词:掘沟工程 深深部开采 含水量 废孔率 

分 类 号:TD217[矿业工程—矿井建设]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象