深厚冲积层冻结段安全快速施工技术  被引量:11

Safe and Rapid Construction Technology in Deep Alluvium Freezing Section

在线阅读下载全文

作  者:魏国强 陈章庆 

机构地区:[1]河南煤炭建设集团有限公司,河南郑州450009 [2]北京煤科联应用技术研究所,北京100034

出  处:《煤炭工程》2015年第2期34-36,40,共4页Coal Engineering

基  金:国家科技支撑项目"深厚冲积层冻结千米深井高性能混凝土研究和应用"(2011BAE27B03)

摘  要:介绍了赵固一矿、泉店风井、赵固二矿、顺河副风井、李粮店主副井等深厚冲积层冻结井施工的实践经验,得出冻结凿井技术水平和经济效益的提高主要体现在安全、快速施工的成果上;同时,从冻结方案设计、机械化水平配置、冻结与掘砌的配合等方面总结了深厚冲积层冻结段安全快速施工技术。Experiences of deep alluvium freezing construction was introduced, based on freezing construction practices of air shafts in Zhaogu No. 1 and Quandian Coal Mine, auxiliary air shafts in Zhaogu No. 2 and Shunhe Coal Mine, and Liliangdian main and auxiliary shaft. The paper pointed out that, the enhancement of freezing technology level and economic benefit was mainly manifested in the achievements of safe and rapid construction. The safe and rapid construction technologies of deep alluvium freezing section were summarized, from the views of freezing scheme design, mechanization level and the coordination of freezing and excavation.

关 键 词:冻结法凿井 深厚冲积层 掘砌速度 施工技术 

分 类 号:TD265.3[矿业工程—矿井建设]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象