作 者:杨家松
出 处:《路基工程》2015年第3期144-148,共5页Subgrade Engineering
摘 要:国内300万m^3及以上的地下洞库高度在24~30m,断面超过300m^2,必须分层开挖,且设置几条进入各层开挖的横向通道。以某地下洞库为依托,对特大型洞室的分层高度、对称爆破成井技术及层间施工方法进行了研究。研究表明:层间采取对称爆破一次成井技术、实施梯段预裂爆破,特大型断面开挖是完全可以减少一个临时通道的设置,既做到安全有保障,又有利于快速施工、节约工程施工成本。The underground caverns not less than 300 m^3 usually in China, which are 24 ~ 30 m high with a section more than 300 m^2, must be excavated in layers with several lateral channels into each layer. Based on a project of underground caverns, this paper discussed the following issues in the caverns with super-large section, i. e. layer height, shaft-forming by symmetric blasting and construction in the layers. The results show that, depending on the symmetric blasting in layers and presplitting blasting in benches, one temporary channel may be reduced in such caverns' setting to ensure safe, fast and economic construction.
分 类 号:TU926[建筑科学—建筑设计及理论]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.229