浅析双层井壁中特大硐室快速施工方法  

Discussion on Speedy Construction Method of Extra-large Chamber in Double-layer Shaft Wall

在线阅读下载全文

作  者:姬良雨 龚望远 任付兴 

机构地区:[1]河南煤炭建设集团有限责任公司,河南郑州450009

出  处:《中州煤炭》2015年第9期74-77,共4页Zhongzhou Coal

摘  要:在石拉乌素煤矿主井箕斗装载硐室施工中,采取了立井井筒冻结段双层井壁中的特大硐室施工方法。采用此方法仅用33 d便完成了箕斗装载硐室的施工,避免了井筒硐室段多次分段套砌内壁的繁琐转换施工工序,减少了井筒内壁接茬缝。既保证了施工质量及施工安全,又缩短了施工工期,效率高,投入成本低。In the construction of main shaft skip loading chambers in Shilawusu Coal Mine, the extra-large chamber construction method was applied in double-layer shaft wall of the vertical shaft freezing section. By adopting this method, it only took 33 days to finish the construction of skip loading chamber. As a result,the tedious conversion of construction sequence in shaft chamber section of muhiple segmental set-assembling inwall was avoided,and the lining linkage in shaft inwall was also reduced. It not only ensures the quality and safety of the construction,but also cuts down the construction period because with high efficiency and low investment cost.

关 键 词:冻结法凿井 双层井壁 特大硐室 整体浇筑 快速施工 

分 类 号:TD264.3[矿业工程—矿井建设]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象