汽机房钢网架结构施工与质量检测验收  被引量:5

CONSTRUCTION AND ACCEPTANCE OF STEEL GRID STRUCTURE OF STEAM ENGINE ROOM

在线阅读下载全文

作  者:王建国 

机构地区:[1]中国电建集团山东电力建设第三工程公司,山东青岛266100

出  处:《建筑技术》2015年第10期919-923,共5页Architecture Technology

摘  要:某电厂汽机房屋架采用钢网架结构,在首跨网架装完后,汽机房行车及时安装就位并投用,利用行车搭建了组合平台,以高空散装法替代高空滑移方案安装完其余钢网架。对周期长的重大施工验收项目,采用分阶段推进项目的管理途径。对此钢网架安装实体质量,通过多方几个阶段联合实地检测,再对比分析不同时段的质量检测数据,可如实反映出网架结构安装质量状况。The steam engine room of a power plant adopts steel grid structure. Traveling crane is installed and put into service immediately after installation of the first span of the grid structure and then assembly platform is erected. High-altitude sliding method is replaced by high-altitude assembly method to install other parts of the grid. Important acceptance requiring long period is managed in different phases. Construction quality of the steel grid structure is inspected by several parties in different phases and these inspection results are analyzed to show the actual construction quality of the grid structure.

关 键 词:钢网架 安装 组织管理 质量检测 

分 类 号:TU758.11[建筑科学—建筑技术科学]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象