出 处:《河南电力》2015年第3期39-41,共3页Henan Electric Power
摘 要:在1000k V南阳站扩建工程中,1000k V串补装置在世界上是首次生产、安装、使用,目前无任何经验可循。1000k V荆门侧出线设计串补平台为6个,单相平台长27米,宽12.5米,重量约60吨,安装高度11.2米。针对荆门侧串补平台安装量大,场地狭窄的特点,采用8吊点双吊钩60吨门型起重机抬吊。门型起重机抬吊作为全新的安装方法为串补平台安装提供了有益的探索,并具有重要的参考和借鉴价值。During the extension project of 1000 k V Nanyang substation, the 1000 k V series capacitor is first produced, installed and used in the world and there is no experience for it. There are 6 SC platform in 1000 k V Jingmen side outgoing line and the single phase platform is 27 metres long, 12.5 metres wide,60 ton weight and 11.2 metres installation high. According to the installation of large amount and the narrow site, the SC platform hoisting adopts eight-point lifting of 60 tons door type crane lifting with 2hook. As a new installation methord, the door type crane provides a useful explorstion for the installation of SC platform, and has important reference value.
分 类 号:TH213.5[机械工程—机械制造及自动化]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.15