基于MIKE21模型的滨海核电厂厂址防洪评价研究  被引量:4

Study on MIKE21 model-based assessment on flood control of site for coastal nuclear power plant

在线阅读下载全文

作  者:纪忠华[1] 胡勐乾[1] 王璐[1] 路雨[1] 杨宇[1] 

机构地区:[1]环境保护部核与辐射安全中心,北京100082

出  处:《水利水电技术》2016年第1期132-137,共6页Water Resources and Hydropower Engineering

基  金:科技部国家软科学研究计划(2013GXS4B075);环保部公益性行业科研专项(1441300000325)

摘  要:为评价典型滨海核电厂厂址防洪安全,采用MIKE21软件模拟外海高潮位顶托条件下可能最大洪水和1 000年一遇洪水的演进过程,分析了厂址北侧排洪通道上所建大件桥梁对洪水的阻水作用。研究结果表明:相比于桥梁的阻水作用,核电厂的防洪安全主要受降雨所引起的厂址上游小流域洪峰强度的控制,即使在设计基准洪水位和潮位叠加可能最大降雨洪水情景下,核电厂主厂区也不受水淹的影响。In order to assess the flood control safety of a typical site of nuclear power plant, the probable maximum flood and the routing process of the flood with a returning period of 1 000 years under the condition of high tide from the open coastal are simu- lated herein with the software-MIKE21, and then the water obstructing effect from a large built bridge on the, flood discharge, channel at the north of the plant site on flood is analyzed as well. The study shows that compared with the water obstructing effec- ring from the bridge, the flood control safety of the nuclear power plant is mainly dominated by the intensity of the peak flow from the upstream watershed caused by rainfall, even if it is under the scenario that the design basis tidal level during flood is super posed by the probable maximum flood caused by rainfall, the main area of the nuclear power plant is to be not impacted by imm- dation.

关 键 词:洪水 核安全 MIKE21模型 桥梁壅水 

分 类 号:TV91[水利工程—水利水电工程] X946[环境科学与工程—安全科学]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象