金属矿山立井多马头门快速施工  

Rapid Construction of Mine Shaft Ingate in Metal Mine

在线阅读下载全文

作  者:周新勍 李加祥 

机构地区:[1]华煤集团有限公司建安工程处,吉林长春130012

出  处:《建井技术》2016年第2期10-12,共3页Mine Construction Technology

摘  要:赤峰柴胡栏子黄金矿业有限公司4号立井,净直径5.5m,井深798m,共设13个中段,各中段设单向马头门。根据以往施工经验,马头门采用分层打眼法,先打上部拱顶眼,再打下部直墙眼,一次爆破成形。通过加强打眼班管理,严格控制各道工序时间,把每个马头门掘砌施工时间控制在了8d以内,实现了快速施工。No.4 Mine Shaft of Chifeng Chaihu Lanzi Gold Mining Company Limited had a net diameter of 5.5mand a depth of 798 m.There were 13 middle sections in the mine shaft and each middle section would have a one way ingate.Based on the previous construction experiences,a slicing borehole drilling method was applied to the ingate.The roof boreholes of the top arch would be firstly drilled and then straight wall boreholes at the bottom of the arch would be drilled.The arch profile would be formed with one blasting operation.With the enhanced management of the drilling shift and a serious control of each procedure time,the excavation and lining construction time of each ingate should be controlled within 8days and thus the rapid construction would be realized.

关 键 词:金属矿山 立井 马头门 伞形钻架 快速施工 

分 类 号:TD264.2[矿业工程—矿井建设]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象