机构地区:[1]中国电建集团华东勘测设计研究院有限公司,浙江杭州311122 [2]浙江浙能水电管理有限公司,浙江杭州310014
出 处:《人民长江》2016年第12期67-70,共4页Yangtze River
摘 要:国内桥机荷载试验中所需的试块一般采用借用的方式,但对于国外特别是欠发达地区的水电项目,试块的采购和运输费时、费力且不经济。针对上述问题,以越南松邦4水电站为例,介绍了利用液压测力器开展桥面荷载试验的基本原理、主要设备、试验步骤及第三方检测机构的检测过程。试验结果表明,液压测力器法能验证桥机各主要机构的技术参数和安全性能,可供国外水电项目的桥机荷载试验借鉴使用。The test blocks used in bridge crane loading test in China are usually borrowed from other hydropower plants; however,in abroad especially less developed area,it is difficult and uneconomical to purchase and transport the test blocks. Aiming at this problem,taking the Song bung 4 hydropower plant in Vietnam as a case,the method of the bridge crane loading test by using hydraulic dynamometer is presented,and the basic working principle,main equipment,test procedure and testing process by the third- party organization are also introduced. The testing result shows that the method can verify the technical parameters and the safety performance of bridge cranes,which is a reference to other oversea hydropower projects.
分 类 号:TK734[交通运输工程—轮机工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.185