高阶段矿石溜井快速形成技术研究  被引量:4

Study on Fast drifting Technology of High-level Ore Chute

在线阅读下载全文

作  者:周礼[1,2] 柳小胜[1,2] 周爱民[1,2] 宋嘉栋[1,2] 詹进 

机构地区:[1]长沙矿山研究院有限责任公司,湖南长沙410012 [2]国家金属采矿工程技术研究中心,湖南长沙410012

出  处:《矿业研究与开发》2016年第8期21-23,共3页Mining Research and Development

基  金:国家科技支撑计划项目(2013BAB02B06)

摘  要:矿石溜井是采场出矿的关键工程,其施工速度直接关系到采场的回采进度。为加快大红山铁矿大结构采场回采进度,提出采用天井钻机施工一条直径Φ1.4 m、高200 m的天井,然后采用吊罐法自下而上扩刷成Φ3 m的阶段矿石溜井。现场应用表明,天井钻机扩帮法成井速度达到80m/月,较普通法成井速度快77.8%,较吊罐法成井速度快45.5%,成井速度显著提升。The ore chute is a crucial project in ore drawing and its drifting speed has a direct effect on the normal mining progress. To speed up the mining progress of large stope in Dahongshan iron mine, the raise boring machine was pro- posed to excavate a chute with diameter of 1.4 m, and height of 200 m. Then, the diameter of this chute was expanded to 3 m from bottom to top by cage raising method. Field appli- cation indicated that the drifting speed was improved obvi- ously and reached to 80 m per month by this method, which had a 77.80% increase than the common method and 45.5% than the cage raising method.

关 键 词:高阶段 矿石溜井 天井钻机 快速掘进 

分 类 号:TD521[矿业工程—矿山机电]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象