特高压交直流投产后山西电网短路电流分析及抑制措施研究  被引量:1

Short Circuit Current Analysis and Suppression Measures for Shanxi Power Grid after UHV AC and DC Projects Being Put into Operation

在线阅读下载全文

作  者:郝鑫杰[1] 程雪婷[1] 郑惠萍[1] 

机构地区:[1]国网山西省电力公司电力科学研究院,山西太原030001

出  处:《山西电力》2016年第4期1-3,共3页Shanxi Electric Power

摘  要:随着山西电网的快速发展,特高压交直流工程的逐步投产使得电网联系愈加紧密,电网容量不断增大,短路电流水平不断提高,导致多个站点出现超标的情况,对电网的安全稳定运行造成不利影响。结合山西电网发展规划,对2017年目标网架的短路电流进行仿真计算,对短路电流超标的站点进行研究分析并提出了可行的抑制措施。With the rapid development of Shanxi power grid and UHV AC and DC projects being put into operation,the total capacity of power grid is increasing.Because the short-circuit current level is getting larger,the allowed value of some power stations exceeded the limits,which has threatened the safe and stable operation of power grid.This paper focuses on short-circuit current simulation calculation according to grid plans in 2017,then feasible suppression measures are put forward for the stations with the current out of limits.

关 键 词:电网 短路电流 抑制措施 

分 类 号:TM713[电气工程—电力系统及自动化]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象